July 13, 2012
Big H Streetscape Project Weekly Update - Week 7 - July 16-20
Big H Streetscape Project Weekly Update - Week 7 - July 16-20
Project updates for next week – pretty much more of the same – removing concrete on the west side of Elm between Adams & Washington and finishing up concrete work in most other areas. All pedestrian ramps at Adams should be complete except the one at the NE corner of Elm & Adams.

Read More
Comments(0)
Rating: 0 star
July 13, 2012
REMINDER - IOOF Cleanup Project work closes alley behind City Hall

The work to abate environmental hazards in the IOOF building at 1106 Adams began on July 9 and will last for approximately 6.5 weeks. During this time the alley behind the building will be closed to through traffic. A detour is set up through the parking lot adjacent to City Hall.

Read More
Comments(0)
Rating: 0 star
June 28, 2012
Big H Streetscape Project - Weekly Update - July 2-13
Big H Streetscape Project - Weekly Update - July 2-13

Due to the Independence Day Holiday, this week’s update will cover the next two weeks, taking us right up to the Crazy Days weekend of July 13 & 14. There will be no work occurring on Adams Ave. until after Crazy Days.

Read More
Comments(0)
Rating: 0 star
June 22, 2012
Big H Project Week 4 Update
Big H Streetscape Project weekly update - June 25-29

Next week, the Project begins the first big “Flip” from Stage One to Stage Two – meaning that in each block section the work transitions to the other side. As concrete gets poured on one side, concrete removal begins on the opposite side of the street in each section on Elm and Depot. Work on Adams won’t start until after Crazy Days in late July.

Read More
Comments(0)
Rating: Zero stars
June 14, 2012
Big H Streetscape Project weekly update - June 18-22, 2012
Big H Streetscape Project weekly update - June 18-22, 2012

New concrete sidewalks will be installed. Saw-cutting of existing concrete & asphalt will occur. Some removal of existing concrete will take place.

Read More
Comments(0)
Rating: Zero stars
June 11, 2012
IOOF cleanup project PUBLIC NOTICE - UPDATED
IOOF cleanup project PUBLIC NOTICE - UPDATED

*UPDATED* Project will begin in early JULY.

Read More
Comments(0)
Rating: 0 star
June 6, 2012
Big H Streetscape project photos posted daily
Big H Streetscape project photos posted daily

New Big H Streetscape Project Photos posted daily on the La Grande Main Street Facebook Page! Check out the daily photo updates online.

Read More
Comments(0)
Rating: 0 star
June 6, 2012
Big H Streetscape project weekly update - Week 2 (June 11-15)
Big H Streetscape project weekly update - Week 2 (June 11-15)

The Big H Project continues with new concrete pouring and concrete removal on sections of Depot Street.

For additional information on what's occuring with the project in Week 2, click here.  For a map of the Week 2 project impact area, click here.

Read More
Comments(0)
Rating: Zero stars
June 1, 2012
Big H Weekly Project Update for Week 1 (June 4-8)

The Big H Project kicks off on Monday, June 4 with saw-cutting throughout the project area and concrete demolition on Depot Street.

For additional information on what's occuring with the project in Week 1, click here.  For a map of the Week 1 project impact area, click here.

Read More
May 14, 2012
Big H Streetscape Project - Community Meeting - May 31, 2012
Big H Streetscape Project - Community Meeting - May 31, 2012

4-6 p.m. at the Fire Museum - 102 Elm St.

Q&A with the project contractor.

Read More
Comments(0)
Rating: 0 star